11 November: a steadier release gate
Releases were held back for about an hour by a test that failed only under load. It is fixed; nothing changed in the product.
Wer ZeroLog nutzt, merkt nichts davon: Geändert hat sich nur ein Test in der Release-Pipeline. Keine Aktion nötig.
Every change to ZeroLog passes the full test suite before it goes live. Since midday one of those tests failed now and then, so releases waited. The cause sat in the test itself: its stand-in provider closed idle connections after five seconds, and when the test machine was busy, the next request picked up a connection that was just being closed.
The stand-in providers in the tests now keep idle connections open for longer, and the failing case was reproduced and confirmed fixed. The product code is unchanged. No action is needed.